Data Centre
Digital Reality Dub 13 Blanchardstown
Republic of Ireland
Months
Construction programme
MW
IT load
Construction of original part of building
Years
First used as an industrial building
The majority of works are internal to the existing building envelope, in order to reorganise the layout and upgrade the overall facility. This includes the removal of internal wall partitions, doorsets, removal of raised access floors, access ramps, ceiling systems. Existing services are to be stripped out and removed.
Externally it is proposed to extend the existing service yard at ground floor level to decommission 2no. existing chillers, 1no. external Generator and 2no. internal Generators (adjacent to yard) and replace this plant with 3no. new Generators. New palisade fencing is proposed and the new generators will extend to c.7.2m in height, slightly above the palisade fence height.
At roof level, it is proposed to replace 3 new chillers behind a plant screen, and they will not be visible from street level.
Client Name: Digital Realty
Project Value: €30m+
Our Role: Project Managers, Cost Management and PSDP
Architect: RKD
M&E: Ethos Engineering
We are changing the world for the better. One space at a time. Take a glimpse at our projects and discover how we’re radically transforming the blueprint for design and construction.